I Want To

Backup Power Generators – Dutch Lake Community Centre and at the Well #1/#3 Booster Station

2024-10-04 – Dutch Lake Community Centre and at the Well #1/#3 Booster Station

Work is progressing and Advanced Electrical Services has successfully completed the generator installation and connection. BC Hydro is now coordinating the next steps, starting with their Inspection Design team reviewing the work done so far. Following approval, the BC Hydro Construction group will finalize the remaining connections. Once all connections are complete, the generator supplier will arrive to commission the system, bringing everything online. Due to the number of parties involved, it is difficult to estimate a completion date, but we will continue to keep the community updated.