This is to advise that Dawson Construction Ltd. will be performing construction work for the Murtle Crescent Reconstruction project in the District of Clearwater.

Start Date: Monday, August 25, 2025

Anticipated Completion: Wednesday, September 10, 2025

Scope of Work: Road excavation, granular base installation, curb and gutter placement, asphalt paving, pavement markings, concrete sidewalk installation, and boulevard restoration.

Traffic Management: Traffic control will be in place throughout construction. Access for local residents and emergency vehicles will be maintained at all times.

For any inquiries, please contact:

Amanda Pfaff – Project Manager 250-819-4511
Dawson Construction Ltd
Email: apfaff@dawsongroup.ca

True – Kevin Kraan 250-826-3527

District – Chad Carmichael 250-674-2257

 

Thank you for your cooperation during this work.